Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Jan 2019

In Jan 2019, INVESTCORP has finished the entire brickwork of the surrounding wall and partitions inside the workshop from the 1st floor to the roof technical floor, completed waterproofing work and heat resistance for the roof.

At present, INVESTCORP is carrying out finishing works such as sandwich panel and painting work at the 1st floor of the workshop. It is expected that all of the internal plastering work will be finished before the Tet holidays. After the Tet holidays, the finishing items will continue to be carried out such as floor epoxy, gypsum ceiling and partition at the 1st floor, finishing work of toilet area of the workshop.

Outdoor items are also implemented in parallel such as concrete roads, drainage system and manholes.