Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Mar 2019

In Mar 2019, at the workshop of the EMS extension project of Meiko Electronics Vietnam Company Ltd, INVESTCORP completed plastering outdoor brick walls and constructing iron partition from the 1st floor to roof floor, completed plastering indoor brick walls in the 2nd floor of the workshop area, finished painting work and epoxy floor of power room.

In addition, other finishing works are being implemented such as painting outdoor brick walls completing 80% of workload, construction of outdoor iron partition and installation of steel door for the work from the 1st floor to roof floor reaching 60% and epoxy painting of workshop floor reaching 90% of workload. Ancillary items such as drainage system and concrete road start being done.

As expected in Apr 2019, INVESTCORP will complete the whole project and hand over to the Owner to put into use.