Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in Mar 2019

In Mar 2019, at the Textile area, INVESTCORP completed all bracing concrete work and is now implementing backfilling and brickwork of the surrounding wall. As expected in Apr 2019, the surrounding wall will be completed plastering work. Assembly of steel structure and construction of factory floor will be carried out at the same time.

At the Dyeing area, after finishing foundation framework and bracing, INVESTCORP is implementing indoor trenches and backfilling of the workshop ground. It is expected that these items will be continued carrying out in Apr 2019 together with assembly of steel structure and concrete of the workshop floor.

At the Office, INVESTCORP has completed foundation framework and bracing and is implementing indoor trenches and backfilling of the office ground.