Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Oct 2018

By the end of Oct 2018, after nearly 2 months of commencement of the EMS extension project of Meiko Electronics Vietnam Company, INVESTCORP has completed all temporary items for construction of the project such as temporary office and temporary fence; completed construction of the entire foundation work and the ground levelling.

At the moment, INVESTCORP is constructing in parallel the ground slab and the reinforced concrete structure of columns, beams and slabs of the 2nd floor.

As expectation, all of the reinforced concrete structure of the factory will be completed by INVESTCORP at the beginning of Dec 2018.