Update construction progress of Myanmar Meranti project’s Ruby in April 2018

The Myanmar Meranti project’s Ruby is commenced on March 1, 2018 with area of the production building of 23,734m2 including MCL, CRV, roll shop and auxiliary items. All of the production and auxiliary buildings are designed with steel structural type, reinforced concrete foundation, walls of 1meter high and corrugated iron above.

After commencing 2 months, temporary items such as office and storage are completed. At present, INVESTCORP Myanmar has finished to 60% of the foundation work for the production building and starts carrying out bracing beam.

It is expected in May 2018, all foundation and bracing beam of the production building will be finished.