Update construction progress of Myanmar Meranti project’s Ruby in May 2018

By the end of May 2018, the Myanmar Meranti project’s Ruby has been completed all the foundation work for the production building by INVESTCORP Myanmar.

At the present time, 60% of the bracing beam has been done and as expected, all of this work will be completed on June 20, 2018.

For the floor of the production building area, INVESTCORP Myanmar is carying out cutting floor piles.