On 5 May 2018, Investment and Development Construction Industrial Corporation INVESTCORP officially commenced the New  pressing factory project of Mitsuba M-Tech Co. Ltd at Thang Long industrial park II, My Hao district, Hung Yen province. The project is built with total construction area of 9,080m2 including pressing building, waste storage, store and roof covering.

mitsuba-06.2018-01

mitsuba-06.2018-02

Rigth after commencing, temporary items such as temporary entrance, road system, water and electrical system, office and many other items such as store, material storage, etc were implemented  by INVESTCORP. By the end of May 2018, the entire temporary items have been completed.

At present, the project is in process of pile test before moving to mass piles and other foundation items. It is expected that the piling work will have been finished by 20 June 2018.