Update construction progress of KMN hot dip galvanizing factory project in June 2018

In June 2018, at the KMN hot dip galvanizing factory project, INVESTCORP Myanmar has completed all tanks and drainage inside the factory, floor levelling is being proceeded. As expectation in July 2018, the whole concrete work of the factory will be finished.

At the office area, the concrete structure work has been done and move into plastering work of the 1st floor and 2nd floor.

At the auxiliary area, the whole foundation item has been completed. At present, column structure and the roof bracing-slab are being implemented. After finishing levelling sand for the internal road, INVESTCORP Myanmar has been carrying out construction of soil layer. Besides, rainwater drainage has been finished to 80% and expected to complete in July 2018.