Construction progress update in May 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
At the end of May 2022, INVESTCORP Land Thanh Hoa Company Limited has implemented the construction of items, including: excavation, dredging of organic soil; embankment of K95 road reached 95% and K98 reached 13% of the contract volume; the cutoff dike reached 70% of the volume, the foundation excavation, mold, and structure excavation have also been completed. Currently, INVESTCORP Land Thanh Hoa is carrying out concrete structure casting and starts to install sewers and trenches.
It is expected that in June 2022, INVESTCORP Land Thanh Hoa will focus on completing items related to the K98 road foundation, concreting the cutoff dike of the talus and the road crossing culvert according to the schedule in the contract.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED