Construction progress update in October 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province
In October, 2022, INVESTCORP Land Thanh Hoa has carried out the construction of crushed stone for the subgrade II layer, reached 80% of the volume, construction and installation of curbs reached 98% and pavement paving reached 81%. At the same time, INVESTCORP Land Thanh Hoa has implemented to plant 98% of the tree volume.
Besides, INVESTCORP Land Thanh Hoa has also completed the construction of sewerage installations and substation installations. The total construction volume reached about 88% of the contract volume.
It is expected in November 2022, INVESTCORP Land Thanh Hoa will speed up to complete the construction of the crushed aggregate base course and carry out asphalt work for the remaining roads; complete the construction and installation of curbs, paving bricks, and the installation of water and electricity supply systems.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police