Construction progress updated in April 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
In April 2023, INVESTCORP Land Thanh Hoa basically completed the works in the traffic category, including the construction of macadam for road surface reached 100%, and asphalt pavement construction reached 100%.
In addition, the Company has also completed the installation of the drainage system. Total output is estimated at 67% of contract volume. According to the plan in May 2023, INVESTCORP Land Thanh Hoa will focus on implementing the spread of asphalt concrete and construction of traffic safety items.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED