Construction progress updated in August 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city
In August 2023, INVESTCORP Land Thanh Hoa constructed the K95 road embankment at 83%; the K98 road embankment construction at 91%; construction of crushed stone foundation grade II at 90%; and construction of crushed stone foundation grade I reached 80%.
In addition, the Company also basically completed the installation of D600 and D400 drainage systems. Total volume is estimated at 48%.
As planned in September 2023, INVESTCORP Land Thanh Hoa will focus on completing construction of crushed stone for the roads; completion of pavement embankment, installation of electrical systems, clean water supply systems, fire protection and wastewater drainage systems.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED