Construction progress updated in December 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1
In December 2022, INVESTCORP Dong Minh has completed the construction of the PCB floor, building and plastering stairs, painting walls, and installing stair railings and roof railings; erecting purlins and corrugated iron walls; finishing tiles, stones, and lobby; erecting steel doors, aluminum and glass doors and glass walls.
For the underground water tank – parking house, INVESTCORP Dong Minh has basically completed the waterproofing system, poured concrete roof, tiled stairs, and installed exterior railing and doors. At the same time, INVESTCORP Dong Minh has also completed 100% of the wall painting and door erection for the electric house and is implementing painting the floor and stairs reached 50%.
Besides, other works of the cooling, air compressor houses, and boiler house were also basically completed by INVESTCORP Dong Minh such as painting walls, installing doors, roof waterproofing and roof heat resistant. It is expected that in January 2023, INVESTCORP Dong Minh will complete the remaining works for acceptance and handover to the Investor.


- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police