Construction progress updated in February 2022– Manufacturing eco-friendly decor product project

In February 2022, INVESTCORP 15 has implemented the construction of factory wall painting, installation of rolling doors and fireproof rolling doors. The system of outdoor 3-step stairs and ramps are under construction. The office area has been started to construct aluminum and glass, aluminum facade panels and drywall partition system by INVESTCORP 15.

It is expected that in March 2022, INVESTCORP 15 will complete the construction of the factory area including painting walls, installing iron doors, ditch cover system and railings. The office finishing package including aluminum and glass facades and aluminum panels are also accelerated construction.

Despite the complicated and prolonged situation of the Covid-19 pandemic with the appearance of many new dangerous variants, INVESTCORP 15 has made efforts, determination, and strives to speed up the progress and ensure the completion of the project within April 2022.