Construction progress updated in January 2022 – Star Villas project
In January 2022, INVESTCORP Myanmar has completed and handed over the villas No. 7 and No. 9.
In parallel, the finishing work includes skimcoat and painting, ceiling and installation of MEP system for the villas No. 3, 6, 10, 12, 14, 15, 16 & 1B are also continued to be constructed. Villa 1A has been completed the erection of the roof structure and plastering work. Outdoor works such as gates, fences, and gardens of villas No. 3, 6, 10, 12, 14, 15 are being completed by INVESTCORP Myanmar.
It is expected that in February 2022, INVESTCORP Myanmar will continue to complete and hand over villas No. 3, 6, 12, 14 and strive to complete villas No. 15, 16, 1A & 1B.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED