Construction progress updated in June 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

By the end of June 2023, INVESTCORP Land Thanh Hoa has completed 100% of the drainage system, lighting, and road surface items. Total output is estimated at 50% of the volume.

According to the plan in July 2023, the Company will focus on implementing the construction of asphalt paving of the entire project and basically completing the items in the contract to ensure the quality and progress of the construction.