Construction progress updated in June 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province
In June 2023, INVESTCORP Land Thanh Hoa completed 83% of the K95 soil road embankment, 91% of the K98 embankment, 90% of the type II macadam foundation, and 80% of the type I macadam one. At the same time, the installation of the drainage system was also completed at 95% of the volume, and the construction of the curb reached 85%.
According to the implementing plan in July 2023, INVESTCORP Land Thanh Hoa will speed up the construction of the road macadam foundations, coming to pour asphalt concrete for the handed-over surface. In addition, in July, the Company will also complete earthworks and paving stone pavement; complete the installation of the electrical system, clean water supply system, fire protection, and drainage system.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED