Construction progress updated in May 2023 – An additional tender package under item
In May 2023, INVESTCORP 15 completed the erection of drywall frames, gypsum ceiling frames, toilet wall tiles, stair paving, and electrical wiring for sockets and lighting systems.
At the same time, the Company is also implementing items such as the construction of drywalls reached 80%, the installation of gypsum ceiling panels reached 80%, painting walls and ceilings reached 50%, and 40% of floor tile installation. In addition, the erection of glass walls and installation of curtains have also started to be implemented by the Company.
It is expected that in June 2023, all of the construction and installation work will be 100% completed by INVESTCORP 15.It is expected that in June 2023, all of the construction and installation work will be 100% completed by INVESTCORP 15.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police