Construction progress updated in May 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province
At the end of May 2023, INVESTCORP 6 basically completed the items of the Four Seasons Rubby Villa, the Bungalow under the lake, and is finishing the interior furniture. For the reception house, INVESTCORP 6 completed the construction of the structure and completed the plastering.
In addition, at the tennis court and laundry area, the structural frame was also completed by INVESTCORP 6. At the Family villa area, INVESTCORP 6 is implementing the construction of floor beams and structures.
It is expected that in June 2023, the Company will hand over the Rubby Four Seasons villa, Bungalow under the lake, and complete the structure of the Family villa area.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED