Construction progress updated in October 2021 – Project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province

In October 2021, the project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province has been implemented and completed by INVESTCORP Land Thanh Hoa 100% of asphalt concrete, 95% of the drainage system and is currently carried out casting safety poles.

According to the plan in November 2021, INVESTCORP Land Thanh Hoa will complete all of the drainage system, complete the paint markings, and install the safety poles and signs for acceptance and hand over of the project to the Investor.