Construction progress updated in October 2022 – Project of Technical infrastructure for residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province
In October 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on constructing road surface and drainage system.
For the road surface, INVETSCORP Land Thanh Hoa has carried out the construction of K98 road leveling, dredging, road foundation excavation, K95 embankment which have achieved 94%; processing and casting concrete components of the drainage system have reached 97%.
It is expected that in November 2022, INVESTCORP Land Thanh Hoa will focus on completing the construction and embankment of K95 and K98 road foundation, implementing the construction of grade II crushed stone base course of the roads that have been handed over the site; completing pavement embankment and rainwater drainage system for the remaining roads and fabricating and pouring components.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police