Construction progress updated in October 2022 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch
In October 2022, INVESTCORP 15 has completed the construction of the foundation and foundation bracing of the main factory as planned to hand over the site to erect the reinforced concrete structure. For the ancillary package and outdoor work, INVESTCORP 15 has also poured concrete of water tank walls, chemical tank walls, foundation and foundation brace of the trash house. Besides, the sewerage is also being constructed by INVESTCORP 15 to return the ground for construction of outside scaffolding.
It is expected that in November 2022, the concrete foundation and walls of the main factory and warehouse area will be poured and built by INVESTCORP 15. The ancillary package and the outdoor work will be completed the tank cap, tank waterproofing, filled the tank to hand over the site for pile withdrawal, hand over garbage house and other works as planned.


- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police




