Construction progress updated in September 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1
At the end of September 2022, INVESTCORP Dong Minh has completed the construction of items of the PCB building such as construction of the 2nd floor columns, the 3rd floor beams, the 3rd floor columns, the roof floor beams, the attic beams, and dismantling formwork of beams and slabs.
Regarding the parking house, INVESTCORP Dong Minh has completed the construction of the beams and slabs on the 2nd floor, the columns on the 2nd floor, the roof beams, and the attic columns.
For the ancillary items such as the electric house, cooling house & compressor house, and boiler house, INVESTCORP Dong Minh has 100% completed staircases and walls. Wall plastering is constructed in parallel.
As planned in October 2022, INVESTCORP Dong Minh will continue to implement the construction of the PCB house, underground water tank, parking house and other ancillary items according to the contract plan.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police