Construction progress updated in September 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province
In September 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on speeding up the contract progress. Items are under construction such as drainage, repair of rubber road surface and sagging.
For the drainage item, in September, INVESTCORP Land Thanh Hoa has implemented 50% of the excavation and installation of trench components; Excavation of old structural road surface, construction of crushed stone surface and asphalt spreading has been completed. Total completed volume is estimated at 26%.
As planned in October 2022, INVESTCORP Land Thanh Hoa continues to accelerate the construction progress to complete the works related to the road surface, drainage system and carry out the construction of asphalt concrete..jpg)
.jpg)
Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED