Construction progress updated in September 2022 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

On September 14, 2022, Investor Sakata and Main contractor Nishimatsu held the groundbreaking ceremony to officially started the construction work under the contract.

In September 2022, for the factory, INVESTCORP 15 has carried out the excavation of the factory foundation and pouring the foundation concrete. At the same time, INVESTCORP 15 is implementing the construction of rainwater drainage sewers, reaching about 50% of the volume.

It is expected that in October 2022, INVESTCORP 15 will complete the construction of the concrete for the factory foundation and bracing to hand over the site to erect the reinforced concrete structure.