Update construction progress – Crystal Martin Vietnam factory project in October 2020
In October 2020, the renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam factory project continued to be constructed by INVESTCORP according to schedule.
At present, INVESTCORP has completed the painting of ceiling beam, installation of outdoor windows and toilet wall cladding. The mockup room has also been constructed. The waterproofing and toilet floor works are being executed in parallel with the ceiling, gypsum partitions and aluminum and glass walls. Wood doors, interior cabinets, mobile partitions, polycarbonate partitions are in the process at the factory.
According to the plan in November 2020, INVESTCORP will carry out the erection of all wooden doors, glass walls, mobile partitions, Vinyl ground and interior cabinets.



- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police