Update construction progress – Golden Land Project Pharmaceutical Factory in Apr 2019
At the present time, INVESTCORP Myanmar is constructing the ancillary area such as guardhouse, pump room, workshop… and underground tank system.
Regarding the outdoor items, INVESTCORP Myanmar has completed the sediment tank and connection trench, completed 85% workload of the internal drainage system and is carrying out backfilling of the internal road. Foundation of the fence and parking house has been completed 100%.
It is expected in May 2019, INVESTCORP Myanmar will continue speeding up construction items to restrict the influence of rainy season to the construction progress.



Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED