Update construction progress – Golden Land Project Pharmaceutical Factory in Apr 2019

At the present time, INVESTCORP Myanmar is constructing the ancillary area such as guardhouse, pump room, workshop… and underground tank system.

Regarding the outdoor items, INVESTCORP Myanmar has completed the sediment tank and connection trench, completed 85% workload of the internal drainage system and is carrying out backfilling of the internal road. Foundation of the fence and parking house has been completed 100%.

It is expected in May 2019, INVESTCORP Myanmar will continue speeding up construction items to restrict the influence of rainy season to the construction progress.