Update construction progress – Golden Land Project Pharmaceutical Factory in Aug 2019

In August 2019, some items of the Kalbe pharmaceutical factory project were completed and handed over to put into use by INVESTCORP Myanmar such as internal concrete road, sedimentation system, pumping pits, parking area and drainage system.

At present, INVESTCORP Myanmar is continuing to construct roof installation and complete auxiliary items, curb casting, door fabrication and some other items.

In September 2019, INVESTCORP Myanmar will focus on completion of tree planting, interlocking bricks and completion of the main gate etc.