Update construction progress – Golden Land Project Pharmaceutical Factory in May 2019
In May 2019, INVESTCORP Myanmar continued implementing workshop and underground tank system. The PIT foundation system has been carried out 80% and will be completed in June 2019.
At the outdoor area, INVESTCORP Myanmar has basically completed the drainage system and 80% of the internal concrete road. It is expected that erection of the fence and installation of the main gate will be implemented and completed in June 2019.
Some auxiliary items such as manholes have been completed 60% and pump pits have been basically deployed etc.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED