Update construction progress in Aug 2017 at Taiyo Nippon Sanso Myanmar Project.
In August 2017, with construction efforts of the Contractor INVESTCORP to ensure progress of the project, at the Office building, INVESTCORP has completed the ground work and is carrying out the gypsum ceiling-partition and painting work. All of the key items will be completed in September 2017.
At the auxiliary areas, the main items are also being completed and repaired for timely handing-over to the Owner in September as expected schedule.
Concrete work for the internal road has been completed 70% of the total workload. The entire concrete work of the road will be finished in September 2017.
For the outdoor rainwater drainage system, INVESTCORP has completed 95% of the total workload.




Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED