Update construction progress in February 2017 – Factory construction project Phase 3 of Yokowo Vietnam Ltd.
At the site of Factory construction project phase 3 of Yokowo Vietnam Ltd, in late of February 2017, Investment and Development Construction Industrial Corporation and the Owner – Yokowo Vietnam Ltd – have carried out inspection for 1/2 of the workshop area. On February 28, 2017, the accepted workshop was put in use.
The other remaining categories of the workshop such as gypsum ceiling and painting are also speeded up to ensure schedule and target for inspection on March 15, 2017.
In addition, the road system and drainage system for the exterior have been basically done. INVESTCORP is taking prompt action to accomplish pavement work and grass planting for the landscape in the early of March 2017.



Other news
- Discussion program celebrating Vietnamese Women’s Day October 20
- INVESTCORP Group celebrates Vietnamese Entrepreneurs’ Day - October 13
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED