Update construction progress in February 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province
In February 2021, INVESTCORP Land Thanh Hoa carried out the construction of concrete structures for drainage systems; construction and installation of sewers, building manholes to collect surface water and gathering macadam to the site.
As planned in March 2021, INVESTCORP Land Thanh Hoa continues to gather macadam; continue construction of sewers and manholes to collect surface water and waste water on roads No. 4, 5, 10 and 11; construction and embankment of macadam grade 2 layer and curbing roads No. 6, 7 and 10; gathering materials and constructing low-voltage power system for roads No. 1, 2 and 3.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED