Update construction progress in January 2017 – Vientiane (Laos) international airport terminal expansion project
By the end of January, 2017, at the site of international passenger terminal West (IPTB West), Vientiane (Laos) international airport terminal expansion construction project has been finished 95% of concrete column, floor beam and stair construction works. As expected, reinforced concrete category being in process will have been accomplished by February 20th, 2017 as progress proposed to the owner and the main contractor.
On the other hands, at the site of International passenger terminal East (IPTB East), the whole foundation category has been accomplished. Backfilling work, blind concrete casting, reinforcement and formwork construction for the foundation beam are being worked on. As planned, casting for foundation and beam category will have been done by February 28th, 2017 and then INVESTCORP will turn into preparing for following construction works namely floor, the first floor column and the second floor beam & slab.
Mentioning the site of the International concourse, reinforcement category has been fully completed. INVESTCORP is in the process of preparing for floor concrete casting with the target completion date in May 2017.





- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police