Update construction progress in July 2020 – Embellishment project of Rung Thong historic sites and landscapes
In July 2020, INVESTCORP Land Thanh Hoa mobilized necessary resources to complete the project and handed it over to the Investor to hold the project inauguration ceremony before the XXV Party Congress of Dong Son district for the term 2020-2025.
The works completed during the month include construction and erection of edging stones for tree rings; brickwork and plastering work, cladding white stones for talus 1; cladding green stones for talus and surrounding fences; construction and completion of equipment installation for guest house and toilets; paving stones 200x200x50mm for the yards around the traditional house; paving stones 150x150x50mm for the yard and granite stones for the three-step staircase in front of the traditional house; planting trees and four season flowers according to the design; other additional items under the direction of Dong Son district’s leaders...
INVESTCORP Land Thanh Hoa has completed the project 56 days ahead of schedule under the contract and handed it over to the Investor for the Inauguration ceremony on July 21, 2020.



- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police