Update construction progress in June 2017 – Taiyo Nippon Sanso Myanmar Project.
After many months of bad weather, until June 2017, managers and engineers at the Taiyo Nippon Sanso Gas Factory construction site have continued to uphold the construction to ensure good quality and timely schedule as required by the Investor and the Contractor.
At the office area, formwork installation and Steel reinforcing work of floors and roofs have been completed. It is estimated that as of July 08, 2017, office roof will be poured concrete. At some other main areas such as gas pumping building, ASP building, etc., plaster-work and rendering have been finished. At present, workers are trying to complete some minor items of the main building.
At auxiliary areas such as power room, septic tank, warehouse, etc., plaster-work and rendering are done at the same time among different areas. In addition, based on requirement of the schedule and nature of each item, subsequent tasks have been quickly deployed.
For outside works, basic main items have been completed. Internal road system has been finished and lined with concrete. In addition, fence and rainwater drainage systems have been completed to 90% of total workload.





- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police




