Update construction progress in May 2017 – Vientiane (Laos) international airport terminal expansion project
Up to the end of May 2017, at the IPTB West, finishing work such as ceiling, gypsum board, paint work, plastering and tiling, etc. has been continuously progressed. External work such as concrete ditches and utility facilities has been developed as well.
At IPTB East, concrete work for slabs & beams of 2nd floor has been completed in some areas, and the rest will be continued on 5th June 2017.
At the same time, at the International concourse, the entire deck and parapet work have been completed. In June 2017, the ceiling work will start to be implemented.





Other news
- Discussion program celebrating Vietnamese Women’s Day October 20
- INVESTCORP Group celebrates Vietnamese Entrepreneurs’ Day - October 13
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED