Update construction progress – Meiko Quang Minh electronics assembling factory project in April 2020
In April 2020, INVESTCORP completed the construction of the factory ground area including sand leveling, base spreading and compaction, moisture-proof nylon lining, installation of formwork and welded wire mesh, casting concrete and finishing concrete surface.
In the factory area, INVESTCORP has completed 90% of the first floor columns and 45% of the second floor ones; completed 55% of the beam and slab at the second floor and is executing beam and slab of the third floor.



Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED