Update construction progress – Meiko Quang Minh electronics assembling factory project in April 2020

In April 2020, INVESTCORP completed the construction of the factory ground area including sand leveling, base spreading and compaction, moisture-proof nylon lining, installation of formwork and welded wire mesh, casting concrete and finishing concrete surface.

In the factory area, INVESTCORP has completed 90% of the first floor columns and 45% of the second floor ones; completed 55% of the beam and slab at the second floor and is executing beam and slab of the third floor.