Update construction progress – Meiko Quang Minh electronics assembling factory project in July 2020
In July 2020, INVESTCORP continued its efforts to carry out the Meiko Quang Minh electronics assembling factory project to hand over to the Investor on time.
In the Main factory, INVESTCORP has basically completed all plastering works, completed the construction of fire-rated doors and main doors etc. Currently, 90% of the aluminum glass windows and paintwork are also completed.
Underground water tank, pump room and ancillary items including guard house, gate, fence and RMU house have been completed. Roads, outdoor drainage systems and grass planting items were completed 100% by INVESTCORP.
Due to some changes, the project will be completed and handed over by INVESTCORP in August 2020.


Other news
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
- INVESTCORP Group Organizes Annual Employee Health Check-up Program 2025
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED