Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Apr 2019
At the end of Apr 2019, INVESTCORP completed all indoor items including architectural items from the 1st floor to the technical floor, epoxy paint, construction of sandwich panel, construction of the door system inside the factory, internal and external wall painting, toilets, gypsum ceiling and partition ect. At present, all indoor items have been handed over to the Owner to put into use.
As expected in May 2019, INVESTCORP will continue implementing additional items such as finishing work of VIP lobby, office area and MTE fabrication workshop, change of LG layout at the 1st floor and finish of the clean room at the 2nd floor.




Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED