Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Dec 2018
In Dec 2018, INVESTCORP has completed all of the concrete structure of the slab and beam including 3 floors with total floor area of nearly 20,000m2. At present, INVESTCORP is constructing the rest such as roof technical room and staircase attic. Topping out work of the project has also completed.
Beside construction of brickwork, finishing work is also promptly carried out such as roof waterproofing, partition at level 1 of the workshop, assembly of purlin system of the outdoor corrugated iron fence etc.





Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED