Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Feb 2019
In Feb 2019, INVESTCORP finished all plastering work inside the workshop, finished epoxy and iron fence at the temporary warehouse. The temporary warehouse is now handed over to the Owner to put into use.
Besides, INVESTCORP also finished construction of panel walls inside the workshop, finished roof handrail and staircase handrail. Plastering work, outdoor iron walls and gypsum partitions around the workshop are positively carried out.
It is expected that in Mar 2019, INVESTCORP will complete the outdoor iron walls; complete the plastering work inside the workshop; complete installation of the gypsum ceiling, doors and windows and continue to finish outdoor systems including drainage system and concrete road system.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED