Update construction progress of KMN hot dip galvanizing factory project in April 2018

In April 2018, at the KMN hot dip galvanizing factory project, INVESTCORP Myanmar has finished 80% of foundation and bracing beam of the production building; finished 9 out of 11 internal chemical tanks. It is expected on May 15, 2018, the remaining tanks and foundation work will be finished.

At the office area, INVESTCORP Myanmar has completed columns of the 1st floor and continued implementing beams and slabs of the 2nd floor.

At present, auxiliary items such as water tanks, weigh station, wastewater treatment tank and gantry crane are under construction. Sand filling of internal road is also being implemented by INVESTCORP Myanmar.