Update construction progress of KMN hot dip galvanizing factory project in August 2018

By the end of August 2018, at the office area, all brickwork and plastering work have been completed by INVESTCORP Myanmar. At present, finish work of the ceiling, partition, floor tiling and internal painting are being underway and expected to finish completely in September 2018.

At the workshop area, after finishing the entire ground concrete work, INVESTCORP Myanmar is implementing brickwork and plastering work of the parapet and will also be finished in September 2018.

Concrete work for the external road system is completed to 40%. The rainwater drainage system is finished at manhole positions. The ancillary houses are carried out finish work.