Update construction progress of KMN hot dip galvanizing factory project in August 2018
By the end of August 2018, at the office area, all brickwork and plastering work have been completed by INVESTCORP Myanmar. At present, finish work of the ceiling, partition, floor tiling and internal painting are being underway and expected to finish completely in September 2018.
At the workshop area, after finishing the entire ground concrete work, INVESTCORP Myanmar is implementing brickwork and plastering work of the parapet and will also be finished in September 2018.
Concrete work for the external road system is completed to 40%. The rainwater drainage system is finished at manhole positions. The ancillary houses are carried out finish work.


Other news
- Discussion program celebrating Vietnamese Women’s Day October 20
- INVESTCORP Group celebrates Vietnamese Entrepreneurs’ Day - October 13
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED