Update construction progress of KMN hot dip galvanizing factory project in July 2018

In July 2018, immediately after completion of all galvanized tanks inside the workshop, INVESTCORP Myanmar has moved to construct ground concrete of the workshop and expected to be finished by 10 August 2018. Also in August 2018, a fence surrounding the factory will be constructed.

At the office area, the entire formwork for the beam and slab has been removed. At present, brickwork and plastering work are carried out and completed to construct gypsum ceiling and partition.

At the auxiliary area, formwork for the roof slab and beam of the power room and pump room is installation. The guardhouse is being completed brickwork and plastering work. The internal road system is being compacted and expected to be finished 50% of the road square in August 2018, the rain water drainage has been finished to 70%.

Other news