Update construction progress of KMN hot dip galvanizing factory project in July 2018
In July 2018, immediately after completion of all galvanized tanks inside the workshop, INVESTCORP Myanmar has moved to construct ground concrete of the workshop and expected to be finished by 10 August 2018. Also in August 2018, a fence surrounding the factory will be constructed.
At the office area, the entire formwork for the beam and slab has been removed. At present, brickwork and plastering work are carried out and completed to construct gypsum ceiling and partition.
At the auxiliary area, formwork for the roof slab and beam of the power room and pump room is installation. The guardhouse is being completed brickwork and plastering work. The internal road system is being compacted and expected to be finished 50% of the road square in August 2018, the rain water drainage has been finished to 70%.


- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police