Update construction progress of KMN hot dip galvanizing factory project in June 2018
In June 2018, at the KMN hot dip galvanizing factory project, INVESTCORP Myanmar has completed all tanks and drainage inside the factory, floor levelling is being proceeded. As expectation in July 2018, the whole concrete work of the factory will be finished.
At the office area, the concrete structure work has been done and move into plastering work of the 1st floor and 2nd floor.
At the auxiliary area, the whole foundation item has been completed. At present, column structure and the roof bracing-slab are being implemented. After finishing levelling sand for the internal road, INVESTCORP Myanmar has been carrying out construction of soil layer. Besides, rainwater drainage has been finished to 80% and expected to complete in July 2018.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED