Update construction progress of KMN Myanmar hot dip galvanizing factory project in Dec 2018

In Dec 2018, INVESTCORP Myanmar has completed casting concrete of the entire factory road, completed and handed over the office, guardhouse and pumping room to the Owner to put in use. The main gate and sub gate, factory’s fence and parking house have also been completed.

At present, INVESTCORP Myanmar continues carrying out additional works of control room, power room and outdoor planting work. As expectation, the control room and power room will be finished in Jan 2019. Some other construction works such as removal of LPG station, assembly of company logo etc. are also being carried out.