Update construction progress of KMN Myanmar hot dip galvanizing factory project in Sep 2018

By the end of Sep 2018, at the office of the KMN Myanmar hot dip galvanizing factory project, tiling work and finish of the gypsum ceiling, painting work and installation of doors are being carried out by INVESTCORP Myanmar. As expectation, the entire office item will be completed in Oct 2018.

At the production area, all plastering work has been completed by INVESTCORP Myanmar. Painting work and other finish works will be implemented and completed in Oct 2018. At present, grinding work for tank surface inside production building is under construction.

Concrete for outdoor road system is continued to construct and complete to 70%. The remaining concrete volume will be done in Oct 2018. Auxiliary items such as pumping room, power room, control room etc. are being finished.

Other news