Update construction progress of Myanmar Meranti project’s Ruby in Apr 2019

In Apr 2019, INVESTCORP Myanmar carried out painting work, false ceiling and other finishing work at the ancillary area and gradually handed over to the Owner.

Regarding the PIT foundation inside the workshop, INVESTCORP Myanmar has completed finishing work for the concrete surface and handed over to the Owner for assembly of equipment. Cleaning work, sealant of ground construction joints and PIT foundation are being implemented and are expected to complete in May 2019.

At the main workshop, INVESTCORP Myanmar has finished ground concrete work around the PIT foundation and moved to implement painting work and finish of toilet areas. At present, painting work has been completed 70% of workload.