Update construction progress of Myanmar Meranti project’s Ruby in April 2018
The Myanmar Meranti project’s Ruby is commenced on March 1, 2018 with area of the production building of 23,734m2 including MCL, CRV, roll shop and auxiliary items. All of the production and auxiliary buildings are designed with steel structural type, reinforced concrete foundation, walls of 1meter high and corrugated iron above.
After commencing 2 months, temporary items such as office and storage are completed. At present, INVESTCORP Myanmar has finished to 60% of the foundation work for the production building and starts carrying out bracing beam.
It is expected in May 2018, all foundation and bracing beam of the production building will be finished.
Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED