Update construction progress of Myanmar Meranti project’s Ruby in Dec 2018

At present, at the Myanmar Meranti project’s Ruby of Meranti Ltd., INVESTCORP Myanmar is implementing construction of floor structure of some auxiliary houses, finish of the internal cable troughs and start of implementing brickwork.

For the additional machine foundation inside the workshop, INVESTCORP Myanmar has cast 40% of the concrete amount and is continuing construction of steel structure, foundation formwork and partition. The remaining foundation excavation is being continued implementing.

At the main workshop, relating items such as casting concrete surrounding machine foundation is carried out and finished according to areas. Brickwork and plastering work have been completed 80% and are being implemented the rest.